On Saturday August 15, a group from the Liverpool Plains met at the Quirindi Pavilion to discuss the planned Queensland Gas Pipeline.
This group has slowly grown over the years and now have a voice that the community are respond-ing too, directing the attention of the public to a major project that has attracted little attention to date.
The Queensland Gas Pipeline project has been present in the Liverpool Plains for over ten years now, with dialogues beginning back in 2007 and initial approval being given in 2009.
This was for a 200 metre wide corridor to run through the state of New South Wales from the Queensland border down to Newcastle, passing through Moree, Narrabri, Gunnedah, Quirindi, Scone, Muswellbrook, Singleton and Maitland on its journey.
The project had been dormant and was due to expire last year when submissions were made by the Hunter Gas Pipeline whom secured an extension to the proposed pipeline project until 2024.
This attracted the attention of many land-holders and concerned community members as it has been a long time since the initial application was made, and many factors have changed since the approval in 2009.
Over 60 concerned landholders and res-idence gathered in a declaration of strength in opposition to the Queensland Gas Pipeline, a sign that the community’s objection is gaining momentum.
The meeting was a mix of the Liverpool Plains residence, ‘Lock the Gate’ representatives who oppose Coal and Coal Seam Gas mining, North West Alliance and a number of special guests.
Jason Allan from the Walhallow Land Council started the proceedings by presenting acknowledgement to country.
There were guest speeches about similar mining projects that were contested and updates from the Liverpool Plains group seeking to halt this pipeline.
David Chadwick from the Western Slopes Group out of Coonamble spoke about his own experience taking on the Western Slopes APA pipeline.
He had a ‘David and Goliath’ struggle with a corporation similar to what we have here in the Liverpool Plains and fought tirelessly to see that proposed pipeline abandoned.
One of the main issues that has been raised by the affected landholders is the type of soil on the Liverpool Plains which could have a negative effect on a pipeline.
A soil scientific firm SoilFutures Pty Ltd released a report in October 2011 for the Mullaley Gas and Pipeline Accord that was a review of soil types and the risks associated with buried gas pipelines.
The study was conducted to the area West of the Liverpool Plains including Bundella up to Boggabri and sited issues with highly expansive soils such as those found along the current proposed pipeline path.
In the conclusion it states “This report demonstrates that there are significant risks associated with place-ment of a buried gas pipeline in the study area incorporating the western Liverpool Plains.
The potential for pipe failure is exacerbated by the extremely deep, highly expansive soils that dominate the area”.
This report was conducted after the initial pipeline approval however with limited communication from the parties involved it is not possible to conclude if these studies have been taken into account with the current assessment of the project and the pipeline route.
Hunter Gas Pipeline responded to the sug-gestion soil type created dangers to the pipeline, they commented “No, the pipeline will be constructed for the conditions, that includes the type of soil, the lay of the land and the propensity to flooding. Pipelines run through many areas prone to flooding, including the Cooper Creek. These pipelines have been in place for decades and no issues have been encountered.”
Another of the many concerns the group have is over the Quirindi and Willow Tree town water supply.
While all parties involved have assured the New South Wales Government and Liverpool Plains Shire Council that there would be no issues with the pipeline running straight through Quirindi and Willow Trees drinking water, the question has to be asked why you would do this rather than avoiding any risk altogether.
These town’s water supply is one of the most reliable in the state, however there is no alternative for these towns if anything should happen to this water source.
Virginia Black put forward a motion on July 18, that outlined the concern that the “current path of the Queensland Hunter Gas pipeline will impact on Council’s Zone One water supply” and also stated the recommended action was to “Request the Mayor and General Manager make representation to the NSW Government and Queensland Hunter Gas regarding the serious nature and impact of the current pathway and ask that an alternative route be sought to ensure the future supply of water is in no way compromised by the pipeline”.
During the meeting one of the LPS Councillors commented “There is no evidence to date that this is in the water supply”. The action group that opposes the Hunter Gas Pipeline have presented a hydrograph using LPSC’s water statistics that appears to show that the pipeline will sit within the towns water supply 60 per cent of the time.
The LPSC discussed the pipeline and rejected that further enquiry was needed. However, there was no evidence or reports presented during the meeting to demonstrate their position, although they have had meetings with all the concerned parties which the community are not privy too.
Hunter Gas Pipeline commented on the proposed pipeline that would run through the towns water catchment, they stated “The pipeline is not affected by being buried in water. The coatings on the pipeline are made from epoxy or poly, the same as pipes used in agricultural situations; therefore, there would be no contamination. This is similar to pipelines being used to transport the water from these aquifers.”
It has been over a decade since this project was first proposed and with that period of time has come an abundance of research and resources that can better inform the Liverpool Plains community of concerns. The NSW Government has deemed this project a Critical State Significant Infrastructure and so the LPSC has recognised this and supported it.
The NSW Government, LPSC and Hunter Gas Pipeline have had many meetings about the project, however the community have not been advised of the agendas or outcomes, so the public remain unaware of research or why decisions have been made. Concerned parties look forward to more information to be provided so that they can better understand the details of this project that is proposed to run through our community.