The Liverpool Plains Shire will receive a temporary rate rise for the next two years as approved by IPART.
IPART’s determination on LPSC’s SRV application
In its determination on Liverpool Plains Shire Council’s application for a Special Rate Variation (SRV), The Independent Pricing and Regulatory Tribunal (IPART) has announced it has approved a two-year temporary increase of 8 per cent per year, inclusive of the rate peg, in 2021/2022 and 2022/2023, to be removed from the rate base on July 1, 2023. In total, this is a temporary increase over the two years of 16.6 per cent. IPART said that in these two years, Council will be able to identify and implement productivity and cost containment strategies to improve its long term financial sustainability.
IPART acknowledged that in recent years, Liverpool Plains Shire Council’s financial performance has been worsening and that it has not had sufficient funds for necessary asset maintenance and renewals. IPART said its determination would provide $1.4 million above the rate peg over the next two years and that the additional income will go towards maintaining and renewing its deteriorating assets, which was identified as a priority by the community. The SRV will be applied across all rating categories, residential, business, agriculture and mining.
IPART’s announcement will result in an increase of 8.3 per cent in 2021/2022 and 8.3 per cent in 2022/2023. IPART acknowledged that many public submissions raised concerns about the proposed higher rates, saying however this needs to be balanced against the Council’s need to deliver services to its ratepayers on an ongoing basis.
IPART assessed Council’s application against the Guidelines issued by the Office of Local Government and determined that it partially met the criteria. It said Council’s financial position will continue to deteriorate even with the additional income from the special variation, and it needs funds to maintain its assets. It acknowledged the impact of the rate increase is significant, particularly given the community’s capacity to pay but this must be balanced against the Council’s need for funding to maintain assets and provide services to the required standard.
The LPSC Mayor, Councillor Doug Hawkins OAM, says he feels their determination is fair and balanced, he takes on board their advice to Council as well as the information received from the community during the SRV information forums and survey process. He said Council will further expedite the efficiency improvements it has committed to delivering to achieve further savings over the next two years before IPART determine on whether the temporary SRV will be made permanent.
“We have not been sitting on our hands this year in regards to becoming a more fiscally responsible Council. Implementing cost containment is not a simple or easy process. Since last September, LPSC’s Management team, GM Jo Sangster, Directors Nathan Skelly and Cian Middleton and Executive Manager Finance Raju Koirala have worked extremely hard preparing Council’s Asset Management Plans and Long Term Financial Plan, which along with the plan to restructure Council’s operations provide the blueprints to identify and deliver savings. I thank them for their huge efforts.
The LPSC Mayor, Councillor Doug Hawkins OAM
“When I became Mayor, in September 2020, and received a briefing on Council’s current position from the General Manager I realised that my fellow councillors and I had to support the management team and auditor’s recommendations to restructure Council’s finances and operations to make it more fiscally responsible and sustainable into the future, part of which required a SRV application.
“The SRV is necessary to catch up with large cost increases over the last six years including cost-shifting by higher levels of government, rising input costs, the requirement to maintain, renew, upgrade and construct new assets, escalating cost pressures, increased community expectations and inflation. Furthermore, if we wish to continue to receive grant funding from the State and Federal governments for major projects, they expect the community to pay what they consider a reasonable level of rates.
“The truth is that if Council had not been successful in gaining millions of dollars in funding through grant applications the many major projects it has been undertaking to provide better sporting and recreational facilities, improved library facilities, projects in most smaller communities and extra funding for roads, all projects that had resulted from community consultation, would not have been possible.
“I thank and pay tribute to my fellow councillors. Advocating and supporting an SRV and implementing the sweeping changes required at LPSC is certainly not the way to win a popularity competition. However, it was the responsible thing to do. Hard decisions had to be taken and my colleagues bit the bullet to put Council in a position to better service the community in the years ahead, to meet the aspirations that community consultation has told us you desire, to further implement local government best practice and importantly to retain our own local identity.
“Your Councillors and the Management Team recognise there is further work to be done to achieve the necessary results and as a team we will remain highly focused on achieving the best long-term outcomes for the community,” Councillor Hawkins concluded.